Proposed Project: Middle School Auxiliary Road Parking Purpose: Provide additional parking (30 spaces) off of the road that connects Charger Drive to the main road at the front of the campus. This is the road where many middle school faculty currently park. Scope of Work: The scope of the work would be to proved 30 asphalt parking spaces with concrete stops. The approximate cost would be between $8,000 and $10,000. Academic / Curriculum Needs: This project has no impact on curriculum Grounds / General Improvements:
Presently middle
school faculty parallel park on the west end of this road.
Parents are using the grass area opposite faculty parking
for picking up students in order to avoid the front of the
middle school traffic congestion after school. Creating a
parking area on both sides of the road would greatly reduce
the risk of parents backing into faculty cars. It would also
add additional room for cars using this room – presently it
becomes a tight one lane road when faculty are parked there. Materials used
will be identical to other parking areas around campus. Funding: Funds would come out of the current facilities budget. Annual upkeep would be minimal: occasional repainting lines and repairing asphalt as needed. Appropriateness:
This area of the
campus is designated academic but adding minimal cost
parking presently produces no negative impact on the
academic program. If this area were ever needed for a clear
academic purpose, changes to the parking area would be very
easy. Given that cars are already parking here – for pick up
and by parents and students related to middle school
athletic field and baseball field use – the paving and some
landscaping would actually improve campus aesthetic. Exhibits:
Submitted By: Jess Garcia on behalf of the Grounds Committee Date: March 27, 2008
Action Taken: Tentatively Approved by the Facilities and
Ground Review Board, March 27, 2008
Next 3 Steps: 1. Add details for landscaping. 2. Inform the community of this project for comment. 3. Submit to executive committee of the Board for approval.
|
|