Campus Master Plan - May 2000 (approved by Board of Directors)
Back to Campus Master Pla
n Home

Back to Committees

May, 2000 - Highlighted items below are completed or in progress (updated 2/28/06)

 

Immediate Need (Begin now) Short-term Need (Begin within 3 years) Long-term Need (Begin within 6 years)
1. Physics Laboratory for US
REC: Begin now or wait and
include in SEA.

2. Sports and Education Annex (SEA)
(to include 2nd gym, dance studio, additional Upper School Classrooms)
REC: Begin now.

3. Strings Instrumental Rehearsal Room
REC: Temporary move to sports & Fitness Center. Move to the Fine Arts Bldg. where dance studio is located, move dance studio to located, move dance studio to SEA.

4. Additional World Arts Classroom
REC: Include in SEA or in Upper
School when SEA is built.

5. One Additional Middle School
Classroom

REC: Need now. Consider splitting
M125 into two rooms.

6. Lighting for the Baseball & Soccer/
Track Fields

REC: Build now.

7. Outdoor Bathroom and Concession
Facility
REC: Build now.

8. Additional Parking Area-30 spaces (Approx.
100 spaces)
REC: Determine location and build now.

9. Improve Vehicular Traffic Flow
REC: Commission an outside professional
to review by July 1, 2000.

10. Storage Needs for Admin. Bldg. Offices
REC: Utilize basement getting climate
controlled, locked areas. Build
by June, 2001.

11. Expansion of Nurse's Office
REC: Possibly expand into adjacent
conference room. Ask Middle
School to prioritize need.

12. Concrete Pad Outside Fine Arts
Backstage Shop

REC: Complete by Sept. 1, 2000.

13. Business Office Workroom
REC: Look for location.

14. Additional Locker Space for Upper
School Students

REC: Place hooks on walls opposite
lockers; build cubbies at end
of halls.

15. Landscaping/External Gathering Areas
REC: Establish a long-term committee
with own budget to address needs.

16. Additional Internal Sitting Areas for
Students
REC: The person responsible for each
each building should address
this need.

 

1. Three add'l US Classrooms for Humanities
REC: Include in SEA or in Upper School
when SEA is built.

2. Ceramics Studio
cost - undetermined
REC: Check feasibility of enclosing and
covering small area outside Fine Arts
Building by June, 2001.

3. Extended Day Space/Meeting Area
REC: Investigate storage area for equipment
and rotate meeting place among classes.

4. Walkway to back stage in theatre
REC: Accomplish within next 3 years.

5. Middle School Meeting Place
REC: Reassess need in two years.

6. Greenhouse/Recycling Compost Center
REC: Ask Science Department to work on
design, needs, size, cost, etc. Committee
will review when plans are submitted.

7. Rehearsal Room for Large Music Groups
REC: Ask Arts Department to reassess needs
after dance studio is moved.

8. Distance Learning Equipment in Teleconference Room
REC: Reassess need in 2 years.

9. Classroom to be Used in Library as Teaching Space
REC: Reassess need in 2 years.

10. Teacher Work/Study Room in Library
REC: Better publicize area already there.

11. Rubberized Surface for Track
REC: Have completed by August, 2002.

12. Dugouts for Baseball Field with Storage
Space for Equipment
REC: Have completed by Spring, 2002.

13. Conveyer Belt for Dish Room Area
REC: Reassess need in one year.

14. Advancement Office needs Additional Office
REC: Reassess need in one year. Could shift IS
from A111 into new office.

15. Upper School Student Lounge
REC: Consider locating one in SEA.

16. Observatory for Telescope
REC: Ask Science Department to determine
mounting location for telescope without
building separate facility. If under $10,000,
fund out of annual capital budget.

17. Amphitheatre
REC: Refer to landscaping committee and fund out of
annual capital budget.

18. PA System and Covered Video Area for Track/Soccer Fields
REC: Reassess need next year.

19. South bleachers in gym reconfigured to allow for
bleacher extension with team and scorer area.
REC: Reassess need in one year.

20. Improvement of Existing Practice Fields
REC: Proceed immediately.

21. Permanent Seating Area for Coaches/Officials
at Cross Country Start
REC: Build by August, 2001.

22. Additional Outdoor Storage for Track & Field
Equipment
REC: Reassess need next year.

23. Display case for autographed books
REC: Complete by June, 2001.

 

[REC: Reassess LT needs in one year and
determine a suitable timeline.]

1. Finish Orchestra Pit

2. Aquatic Research Area (pond)

3. Six Foreign Language Classrooms
REC: Include in SEA or Upper School
when SEA is built

4. Mobile Shelving for Library Books

5. Storage area for textbooks, educational
materials, furniture, etc

6. Wireless Network Stations Outdoors

7. Plastic Bleachers for Soccer/Track

8. Additional Game and Practice Fields

9. Charger Head Logo put on Fitness Center
Lobby Floor

10. Word "Charger" landscaped into hill on south
end of soccer/track facility.

 

 

 

Cary Academy
1500 N. Harrison Avenue
Cary, North Carolina 27513
Phone: 919-677-3873
Fax: 919-677-4002
Copyright (c) 2001 Cary Academy Cary, NC, USA. All rights reserved.
webmaster@caryacademy.org